Power outages and backup power
Hooking Up Generator to House - Which Hookup Fits Your Home, and the Outage-Day Order
Updated October 17, 2026 - 8 min read - Rainy Day Plan
The short answer
A generator connects to a house through a transfer switch or an interlock, fed by an outdoor power inlet and installed by a licensed electrician. On outage day you run one cord to the inlet and switch over in order. If everything you need has a plug, cords alone do the job. Never plug a generator into a wall outlet: power runs backward onto the lines.
Which hookup fits your home
Start from what has to run, not from the hardware. If you haven't added up the watts yet, our page on what size generator you need shows the sum.
| Your case | What fits | Why |
|---|---|---|
| Everything you need has a plug: fridge, freezer, lamps, chargers | No hookup. Run outdoor-rated extension cords from the generator's own outlets, and give a heavy draw like a window air conditioner a cord to itself | Nothing gets installed, and with nothing wired in there may be no permit or inspection to arrange |
| Something you need is wired into the house: furnace fan, well pump, water heater | A panel hookup, through a transfer switch or an interlock | An extension cord can't reach something that's wired in. A transfer switch can power it, and it generally takes a generator of 5,000 watts or more |
| Your generator has no larger outlet, often marked 220V or 240V | Cords | The hookup cord plugs into that outlet. Generators under 5,000 watts generally don't have one, so check yours, and ask the electrician whether it matches the inlet |
| Someone else may have to run it, or you want it simple in the dark | A manual transfer switch | You and the electrician choose the circuits ahead of time, so only those can come on |
| You want to pick circuits on the day, and you'll watch the load yourself | A panel interlock, if your panel and your local code accept one | It feeds the whole panel |
If the names are new to you:
- The power inlet is an outlet on an outside wall, near where the generator will sit. One cable runs from the generator to it. That cable has to be rated for your generator, so have the amperage it needs labeled and you'll get the right one.
- A manual transfer switch is a small breaker panel next to the main one. It moves your chosen circuits from utility power to the generator and keeps generator power off the utility lines.
- An interlock is nothing more than a metal bracket on the main panel. It covers the main breaker so nobody can turn it on while the generator is running. The main breaker and the generator breaker are never on at the same time.
- The generator breaker in the panel is sized to the generator: 30, 60 or 100 amps. A 30-amp breaker at 240 volts goes with a generator of about 7,000 watts or smaller. Ask the electrician which one yours needs, and have it written on the inlet.
All five rows are about a portable generator. A standby generator is a different job: a licensed electrical contractor connects it to the house permanently, and an automatic one starts by itself in an outage, with its own automatic transfer switch. Ask for its spot at least 25 feet from every window, door and vent, soffit vents included. The rest of that job is on whole house generator.
The electrician's part, and the question to ask about each
The panel work belongs to a licensed electrician, so you won't find wiring steps here. Your side of it is knowing what to ask.
| The electrician handles | Ask before the work starts |
|---|---|
| Whether an interlock works with your panel and meets local code | "Can my panel take an interlock, and does this town accept one?" |
| The permit before the work and the inspection after it | "Who pulls the permit, and when is the inspection?" |
| The inlet on an outside wall, which has to be a listed power outlet, and the switch or interlock | "Does the inlet match the large outlet on my generator, and will you label the amperage the cord needs?" |
| A shutoff at the meter, if the job needs one. The city then has to approve the work before the power company turns the power back on | "Will the power be off, for how long, and who calls the utility?" |
| Permanent signs at the main disconnect and at the meter, saying what kind of backup source the house has and where it is | "Will you also label the breakers and write out the switch-over order for this panel?" |
Towns differ on the details in rows two to five, so the questions in the right-hand column are how you find out yours.
Your own part is shorter:
- List what has to run and add up the watts.
- Choose the circuits with the electrician.
- Decide where the generator will sit before the inlet goes on a wall. The reason is further down.
- Book early. The work usually takes less than a day, but electricians are hard to find once a big storm is in the forecast. You can also ask your utility company whether it installs a transfer switch.
Outage day: the switch-over order for each device
Report the outage to your utility first, then follow your column. It's the general pattern, so if the generator's manual or the order your electrician writes for your panel says otherwise, go with those.
| Step | Manual transfer switch | Interlock |
|---|---|---|
| 1. Set up | Set the generator at its spot outdoors and connect its cord to the inlet | The same |
| 2. Clear the load | Turn off or unplug everything | Turn off every breaker in the panel, then the main breaker |
| 3. Start | Start the generator and let it come up to speed | The same |
| 4. Switch over | Put the transfer switch in the generator position | Slide the interlock over, then turn the generator breaker on |
| 5. Add loads | The largest motor first, then the next load once that motor is up to speed. One circuit at a time | Turn back on only the breakers for what matters most, such as heat, the water pump and the refrigerator, one at a time. Large loads like the range or dryer stay off |
| 6. Utility is back | Put the switch in the normal position, then stop the generator, then unplug the cord | Generator breaker off, slide the interlock back, main breaker on, then stop the generator. Last, turn on the breakers you'd left off, one at a time |
With an interlock the whole panel is live, so the load is yours to watch. Turn on too many breakers and the generator will typically shut off. If it does, turn some off before you start it again.
Step 6 starts when the utility is back, so you need a way to tell. A transfer switch that moves only your chosen circuits leaves the rest of the house on the utility side. So leave a lamp switched on, on a circuit you didn't move, and it lights when the power returns. With an interlock the main breaker is off, so nothing indoors can tell you. Check the utility's outage map or its text alerts, or look for a neighbor's lights.
Copy your column onto a card, have the electrician correct it for your panel, and tape it inside the panel door.
On cords alone there's no switch to move, so the day comes down to the cords and the order:
- Use grounded, three-prong cords, each rated in watts or amps for what it feeds. If one is rated too low, swap it for a cord with heavier-gauge wire. An overloaded cord can overheat and start a fire.
- Give anything with a motor the shortest cord that reaches from the generator's spot. A very long one can leave the motor short of voltage and damage it.
- Unplug or switch off everything first, start the generator, then start the largest motor. Add the next load once that motor is up to speed.
The rest of the day - the fridge clock, the phones, the first night - is in what to do when the power goes out.
A cord with a plug at both ends: what it does, in order
The shortcut is a cord with a plug at each end, run from the generator to a wall outlet or the dryer outlet. Here's what happens when someone uses one.
- As soon as one end is plugged in, the bare prongs on the other end can be live.
- Power runs backward through the panel and out to the street. It can make wiring live for great distances. On the way, the transformer outside can work in reverse and step the voltage up, which can electrocute people working on the line.
- Inside, the power goes around some of the circuit protection built into the house.
- When utility power returns, the two sources meet. That can start a fire in the home's wiring, or make the generator burn or explode.
"But I'd turn the main breaker off first." That deals with steps 2 and 4 for as long as the breaker stays off, and nothing holds it there. Holding it there is all an interlock does. The bare prongs and the bypassed protection are still there either way. The answer doesn't change: these cords should never be used.
Choose the generator's spot before the inlet goes on the wall
The inlet belongs near where the generator will be set up, so the spot comes first. The generator runs outdoors only, at least 20 feet from the house, with its exhaust aimed away from windows, doors and vents. If the inlet lands on a wall where the cord can't reach a spot like that, the generator ends up too close.
Whichever hookup you end up with, these hold too:
- Never in a garage, basement, crawlspace or shed, even with the doors and windows open, and not on a porch or in a carport.
- It stays dry. In rain it runs under an open-sided canopy, and it still needs 3 to 4 feet of open air on every side and above. Rain gets its own page: running a generator in rain.
- Put battery-powered or battery-backup carbon monoxide alarms on every level and outside every sleeping area. If one sounds, get everyone outside, then call 911. They're on our power outage emergency kit list.
Questions people ask
Can I do the generator hookup myself?
Not with steps from us. The work at the breaker panel is a job for a qualified or licensed electrician. Where a town only recommends an electrician, the permit and the inspection can still be required. Ask your local building department whether your town lets an owner pull that permit.
Sources
Every number in this article comes from these public sources, and we checked each one before it went up.
- Consumer Reports - Why a portable generator needs a transfer switch, updated January 2024
- DOE Building America Solution Center - Generators for back-up power during outages
- City of North Port, Florida, Building Division - Generator permit guidelines
- OSHA - Portable generators fact sheet FS-3286
- Wisconsin DATCP - Generators fact sheet, revised October 2023
- FEMA - Generators at home fact sheet, October 2022
- NDSU Extension - Standby electric generators
- CDC - Carbon monoxide poisoning basics
- CPSC - What to know about generators and carbon monoxide, 2022
- CPSC - Warning to stop using male-to-male extension cords, news release 26-363, March 2026
- City of Chino Hills, California - Transfer switch for generator connection
- Purdue Extension, Indiana 4-H - Electric level 5, generator interlocking circuit breaker kit
- CPSC staff - Stationary generators, the carbon monoxide poisoning hazard and recommendations for mitigation, June 2025