Power outages and backup power
Whole House Generator Installation - The Steps, the Permits, the Waits and the Spot
Updated October 17, 2026 - 9 min read - Rainy Day Plan
The short answer
On a whole house generator installation, a licensed electrician wires the generator and its transfer switch, the gas line goes in under the same permits, and the building department inspects the work. Your part: the list of what must run, the spot, and the questions for each bidder. Push hardest on the spot: the usual 5 feet is a fire distance, and exhaust has traveled 25 feet.
Who does what, in the order it happens
- You write down what has to run in an outage. That list tells the contractor whether to quote the whole house or a handful of circuits. Work the sum first with what size generator do I need.
- You hire a licensed contractor who has done generators before, after you've looked the license up yourself. How to do that is further down.
- The contractor draws the plan and applies for the permits. The building department wants the plan before the pad is poured, not after.
- Someone calls 811 a few days before any digging, and the buried utility lines near the trench get marked for free.
- The crew sets the pad, the generator, the transfer switch, the wiring and the fuel line, following the maker's installation instructions. If the meter has to be opened or the service shut off, the utility gets a call first.
- The inspector comes, often more than once. Ask whether your power stays off until the work is approved, as it does in one Florida city.
- The utility hears about it. Call once the unit is in, so line workers know a generator is at that address.
- Before the crew leaves, have them show you, and anyone else who lives there, how to switch the control off for an oil check and back to automatic, and what the status light shows when it's ready and when it warns. Then watch the house move over to the generator and back once. When they go, check that the control is on automatic.
Everything hangs on one part of step 5. A standby generator feeds the house wiring only through an automatic transfer switch that a licensed electrician installs under a permit. An interlock, a bracket on the main panel that someone slides over by hand, belongs with a portable: it can't move the house over with nobody home. The switch cuts the house off from the power line before it connects the generator, so no power flows back out to the crews working on the line.
The fuel line in that step runs to the gas meter, in pipe sized for what the generator burns flat out. Or it runs to a propane tank on your lot that keeps set distances from buildings, property lines and other tanks. With a tank, plan for a supply that lasts several days.
Finding names, and checking them yourself
Attaching a generator to a home's wiring is a job for a licensed electrician only. So your work is finding a licensed, insured contractor who has installed generators before. Ads and directories give you names and nothing more. Better ones come from:
- The maker's dealer locator, which lists the installers it has approved near you. That approval proves little. After Ida, 57 households where exhaust got indoors were asked who had installed their unit, and 32 named a maker-approved company.
- Neighbors with a unit. Ask who did the job, whether it passed its first inspection, and who chose the spot.
- Your building department's permit search, if it has one. Old generator permits show who does this work locally.
A store selling the unit may offer to arrange the installation. Ask which company will do it.
Then, before anyone visits:
- Look the license number up with the state or county board that licenses contractors. Note its status and the work it allows. No listing, no visit.
- Find out who runs the gas or propane line. That's a second trade, a gas fitter or plumber, and a partner company's license gets the same lookup.
- Ask for a copy of their insurance.
- Ask your local consumer protection office about complaints, and search the company's name with "complaint", then with "review".
If a bidder wants you to pull the permits yourself, take that as a warning sign.
What your building department will want
The contractor puts the permit package together. Before it goes in, check that it holds:
- A drawing places the generator, and the fuel tank if there is one, with how far each sits from buildings and property lines, plus the pad and its anchoring.
- The electrical sheets show the transfer switch, the panels, the generator's kW rating and the load calculation, counting every load served and the current motors draw as they start. The load on the switch can't be more than the generator's rating.
- The fuel type and its source are named. The gas piping goes on the plans with the clearances at the gas meter.
- The maker's specs go in as well.
Then ask your own building department where the unit may sit, before the plan is drawn. Here's how much the answers vary from place to place:
- Which yard is allowed? The rear or side yard, in one city.
- How far from the property line? 5 feet from the rear and side lines in that city. In one county it depends on the zoning district.
- How far from windows, doors and vents? In that county the exhaust sits 10 feet from them. Another city gives no number and goes by the maker's instructions.
- Does it have to sit above the flood level? In that county, yes.
On inspection day the installer should be there with the electrical plan, the maker's instructions and the load calculations. Inspectors may also check that your smoke and carbon monoxide alarms work.
A permit doesn't settle the spot, though. None of these rules asks for the 25 feet below, and one county's zoning rule sets no minimum space at all between the house and the generator.
Ask for 25 feet, not the 5 on the plan
When the contractor walks you to the spot:
- Ask for a spot at least 25 feet from every window, door and vent, soffit vents included. Our own minimum is 20 feet from the house, for any generator.
- Look up. The eaves count: after Hurricane Ida, carbon monoxide (CO) came in through attic vents in 46 homes, 45 of them soffit vents under the eaves.
- Check which way the exhaust points. One Ida unit sat 26 feet out with its exhaust facing the house, and CO still got inside.
- If the lot can't give 20 feet from the house and 25 feet from every window, door and vent, stop and look at another way to back up the house before you sign. Your contractor may tell you the code allows less. It does.
- Put battery-powered or battery-backup carbon monoxide alarms on every level and outside every sleeping area. If one sounds, get everyone outside, then call 911.
The plan may well show 5 feet. That's the fire standard installers work from, which asks for at least 5 feet between the generator and openings in walls, with exceptions that allow less. It was set to limit fire, and no code or standard deals with CO from a standby generator. A local code may ask for more, like the county above with its 10 feet. For CO, a standby unit goes 25 feet or more from any opening into the house. Even a portable runs at least 20 feet out.
The 25 feet comes from Hurricane Ida in 2021. Reports came in on 256 Louisiana homes where CO got indoors, and in 105 of them the source was the house's own standby unit. Where the distance to the house was known, 51 of 56 of those generators sat 6 feet or less from it. Where the distance to the opening was known, 41 of 49 sat more than 5 feet from it, beyond the fire code's number, and the exhaust got in anyway. It reached openings 25 feet or more away and climbed more than 10 feet.
In a flood zone, the switch goes up with the generator
In a flood zone the generator goes above the base flood elevation, the height a flood with a 1-in-100 chance in any year is expected to reach, and your local floodplain manager can tell you yours.
Raising the generator alone isn't enough. The switch and the electrical gear it feeds go at least as high, or a flooded switch leaves a dry generator useless, as happened in Cedar Rapids, Iowa, in 2008. Finding your height and the ways to raise a unit are on generator in flood zone.
Where the weeks go
Four waits sit with someone other than your contractor, and they come in this order. Permit rules don't put days on them, so ask locally.
- Plan review comes before the permit. In one South Carolina county, every generator needs it, with a site plan and a single-line electrical diagram.
- One job can mean several permits. There, the stand, the slab, the electrical work and the gas each get their own.
- Inspections are booked a day ahead and come in order: there, the gas rough-in has to be approved before the electrical final can be called.
- Power to the new system waits for the last sign-off. Every permit has to be finaled before it's released.
Ask the contractor for a date on each of those, not one date for the whole job, and book in a quiet season rather than the week a storm is forecast.
What the price turns on
Most of the bill is labor and materials, not the machine, and a smaller unit barely moves it, since installing a small one or a large one comes out close. The spot drives a lot of the rest: every foot between the generator and the panel or gas meter is wire, conduit, pipe and trench.
So compare bids on the work, not on the box. Ask several companies for written estimates that spell out the job, the materials, a finish date and a price. Hand each one the same seven lines to price: the generator, the transfer switch, the electrical work, the fuel hookup, the site work (pad, anchoring, any raised platform), the permits and inspections, and the yearly service. Check the scope before the price: same size, same circuits, same spot, same fuel work, or the totals can't be compared. A blank line isn't free, so ask whether the permits, the gas work and the pad are inside the number or come later. Don't take the lowest total by default, and when one bid lands far under the rest, ask why.
The contract, and when the money changes hands
Put the deal in a written contract, whether or not your state requires one. It names the contractor, with address, phone and license number, sets a start and a finish date, and holds every promise you were given out loud. Never sign one with blanks left in it.
Don't pay it all at the start. Some states cap the down payment, and a state or local consumer office can tell you the limit. The last payment waits until the job is finished and you're happy with it, and with a generator, finished means the final inspection in step 6 has passed. If the contractor offers a loan, see what other lenders would offer first.
If you sign at home, the Cooling-Off Rule usually gives you until midnight of the third business day to cancel and get all your money back, and the seller has to give you the cancellation form in two copies. Exceptions apply, such as a deal made at the seller's usual place of business.
Seven questions for every bidder
- Who pulls the permits, and will you be at the inspection?
- May I see the load calculation, and which circuits will the switch feed?
- How far is the unit from the nearest window, door and soffit vent, and which way does the exhaust point?
- Are the gas meter and pipe sized for full load?
- Is the unit above the flood level, and the switch at least as high?
- Who calls 811, and who calls the utility?
- How long is the power off on install day, and when is each inspection?
Sources
Every number in this article comes from these public sources, and we checked each one before it went up.
- CPSC staff - Stationary generators, the carbon monoxide poisoning hazard and recommendations for mitigation, June 2025
- City of San Jose - Standby generator permit requirements, updated April 2026
- Miami-Dade County - Generator permits
- City of North Port, Florida, Building Division - Generator permit guidelines
- Charleston County, South Carolina, Building Inspection Services - Generator form
- Utah Be Ready - Generator
- NDSU Extension - Standby electric generators
- PHMSA - Calling 811 before you dig, 2013
- Mississippi State University Extension - Disaster relief, emergency standby electric generators, Publication 2972
- FEMA - Mitigation for homeowners
- FEMA - Design considerations for improving critical facility functionality during flood events, 2009
- CDC - Carbon monoxide poisoning basics
- CPSC - What to know about generators and carbon monoxide, 2022
- CPSC - Caution when using portable generators, Tropical Storm Ian, 2022
- Consumer Reports - Generator buying guide, updated October 1, 2026
- FTC - How to avoid a home improvement scam, 2022
- FTC - Buyer's remorse, the FTC's cooling-off rule may help, 2025